Syrup Room


Richlands

2022

Food & Beverage


"Bubbles" deliver for F&B Client

In a factory operating environment, time is money, that’s why Box&Co had just 10 days to complete a job that would normally take six weeks for a multinational Food & Beverage client.

To get a jump on the project, “bubbles” were created to allow the team to do early work in a live environment before the plant was shut down for the main works schedule.  The project saw the relining of damaged in-ground concrete trade waste pipe, with Box&Co providing a custom equipment “feet to floor” joint solution.  Approximately 900m3 of new epoxy floor was laid in very challenging conditions.